Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Access Road

 

21 June 2002

Construction work on the access road "Höhenstraße" has been completed. An inspection was carried out on 21 June 2002. Strengthening of the retaining walls and the necessary reinforcement of the bridges at the bottom of the access road have been carried out with the help of experts. The "Höhenstraße" is ready for transportation of the turbines pieces.

The excellent achievements of the planner DI Neuber and the construction company Lang&Menhofer should be mentioned. Motivation, adhering to the time schedule, excellent quality, perfect co-operation with the public and a talent for organising were the cornerstones for success of this part of the project.

   
 

Access roads inside the wind parkRemoving of grass blocksRetaining stone wallsStrenghtening of access bridge

   
 

Building of the roads within the wind park is now underway. The alpine humus surface is carefully removed in blocks and stored. When the embankments are completed, the blocks will be put back into place as quick as possible in order to keep disturbance of the environment to a minimum.

   

 
 

21 June 2002
10 June 2002
20 May 2002
30 April 2002
Data + Building Progress