Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Access Road

 

20 May 2002

Levelling of the rocky "Lauskogel" was an important step. 100% of the material was broken down by a mobile breaker and used for construction of the road.

This use of local resources is environmentally friendly, reduces the number of truck trips and therefore saves gasoline.

   
 

Mobile breakerRemoving the LuaskogelConstruction of sharp bends

   
 

Levelling the "Lauskogel"'

Building the turnouts

   
 

Widening of the curves of the "Höhenstraße" is in progress. The necessary retaining walls are constructed with heavy rocks which give them a natural look.

   

 
 

21 June 2002
10 June 2002
20 May 2002
30 April 2002
Data + Building Progress