Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Access Road

 

30 April 2002

Work on the adaptation of the access road began on 22 April 2002. An extensive phase of this work is construction of the road around the Steinwidder farm.

   
 

Road around the "Steinwidder"Excavation works

   
 

The snow at higher places is removed, at the same time excavation work at the lower end of the access road is underway.

   
       
 

Muddy soilRoad clearing teamStill hard winter

   
 

At an early point in the project, access to the site is necessary for surveyor work and for the construction companies.

   

 
 

21 June 2002
10 June 2002
20 May 2002
30 April 2002
Data + Building Progress