Data + Building Progress
Total length: 11.80 km
To be paved: 5.10 km
 |
|
Building Progress
|
Access Road "Höhenstraße"
Roads in the wind park
|
completed
completed
|
|
5 July 2002
|
Storage area at foot of the "Höhenstraße"
|
completed
|
 |
Main work on the access road: adaptation of the curves so that
the inside radius amounts to 8 m and the outer radius to 15 m.
The turbine components will be intermediately kept at the storage
area at the foot of the "Höhenstraße". From
here they will be transported by helicopter or by way of the "Höhenstraße"
to the wind park site.
The adaptation of the access road and construction of new roads
inside the wind park have been executed by Lang & Menhofer BauGmbH
& CoKG.
|