Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Access Road

 

Data + Building Progress

Total length: 11.80 km
To be paved: 5.10 km

Building Progress

Access Road "Höhenstraße"
Roads in the wind park

completed
completed

5 July 2002

Storage area at foot of the "Höhenstraße"

completed

Main work on the access road: adaptation of the curves so that the inside radius amounts to 8 m and the outer radius to 15 m.

The turbine components will be intermediately kept at the storage area at the foot of the "Höhenstraße". From here they will be transported by helicopter or by way of the "Höhenstraße" to the wind park site.

The adaptation of the access road and construction of new roads inside the wind park have been executed by Lang & Menhofer BauGmbH & CoKG.

   

 
 

21 June 2002
10 June 2002
20 May 2002
30 April 2002
Data + Building Progress