Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Foundations

 

17 July 2002

The last foundation was put in on 17 July 2002. One last check to make sure that the reinforcement and anchorage of the tower foundation sections were properly prepared and the pouring of concrete can begin.

   
 

Reinforcement of foundationLast foundation to be concreted

   
 

In order to keep the tower foundation sections clean, they are kept wrapped in plastic.

After the concrete has hardened (about 3 days), the formwork is removed and the building pit filled in.

   
 
Backfill of foundation pitRestoration of ground surfaceFoundation ready for tower erection
   
 

The blocks of ground surface are put back into place as soon as possible. This will give the grass and earth enough time before winter to regenerate.

   

 
 

17 July 2002
21 June 2002
10 June 2002
Data + Building Progress