Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Foundations

 

21 June 2002

A lot of rock near WT 3.

DI Trauttmansdorff visits the construction site and is satisfied with the progress being made but also sees the difficulties of working at the site. Excavation and backfill work is under way.

   
 

Trauttmansdorff checking the rocks hardnessTrauttmansdorff visits the siteBackfilling

   
 

The foundation near WT 7 has been completed and the pit filled in. Special attention is made to place the blocks of humus back into their original position. After the pits are filled, only the foot of the tower is visible.

The walls enclosing the open pits must stand up to strong winds.

   
 
Earthing rodSite fences at pitsRestoration of ground surface
   
 

It is only natural that the foundations have an earthing system. Where the earthing wire enters the ground, it is wrapped in Denso tape to keep it from chemically decomposing.

   

 
 

17 July 2002
21 June 2002
10 June 2002
Data + Building Progress