Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Foundations

 

10 June 2002

Excavation work in difficult ground with the ground quality 6 (rock).

The flat and compacted floor of the foundation pit is covered with a 10 cm bedding concrete.

   
 

Excavation of foundationBedding concreteFormwork and reinforcement

   
 

Afterwards the upper and lower reinforcement is brought into place. The earthing system and cable protection pipes, for cables which will be put in at a later date, leads between both reinforcements up to the middle of the foundation section.

The foundation section weighs 9.4 tons. Alignment of the foundation sections has to be done with a preciseness of 2 mm.

   
 
Lower reinforcement1st tower segment put in placeAlilgnement of 1st tower segmentFoundation WEA 7: Concreting completed
   
 

After the concrete has been poured, the fresh concrete surface is protection by a plastic tarpaulin to prevent the concrete from drying up. Due to the strong winds, the plastic tarpaulin is weighted with sand.

   

 
 

17 July 2002
21 June 2002
10 June 2002
Data + Building Progress