Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Wind Turbines

 

3 October 2002

Assembling of the wind turbines was not going according to schedule due to delivery delays on the part of the manufacturer. But then on Sept. 23rd the first nacelle was installed.

   
 
Wind energyWind farmLifting nacelleVestas in the air
   
 

In spite of snowfall, the wind turbine went into operation on Friday, Sept. 27th and this meant that over 100 MW of wind power capacity had been installed in Austria.

   
 
SupervisionCrane and Wind TurbineSnow in September
   
 

On October 7th a second Vestas team would join the crew to make sure that the turbines would go into operation as soon as they were ready. As the snow showed, winter is just around the corner at 1,900 meters above sea level.

   

Wind Turbine
 
 

6 December 2002
31 October 2002
8 October 2002
3 October 2002
30 August 2002
5 July 2002
21 June 2002
Data + Building Progress