Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Wind Turbines

 

21 June 2002

Manufacturing of the turbines is in full speed. Gigantic halls are necessary for finishing the rotor blades. Special care is taken to ensure that the rotor blade surface is perfect, even the smallest unevenness is smoothed.

   
 
Finishing of blade surfaceBlade construction at Vestas
   
 

One set of rotor blades will receive a special layered surface construction. These three blades have already been transported from Vestas to a specially rented hall in Linz where they will obtain this layered construction.

Afterwards the blades will be transported from Linz to the intermediary storage area at the foot of the "Höhenstraße" by trucks. By the 25th and 26th of July all the rotor blades will have arrived for transportation by helicopter to the wind park site.

Erection of the towers will begin on 2 July 2002, starting with wind turbine 7.

   

 
 

6 December 2002
31 October 2002
8 October 2002
3 October 2002
30 August 2002
5 July 2002
21 June 2002
Data + Building Progress