One set of rotor blades will receive a special
layered surface construction. These three blades have already been
transported from Vestas to a specially rented hall in Linz where
they will obtain this layered construction.
Afterwards the blades will be transported from Linz to the intermediary
storage area at the foot of the "Höhenstraße"
by trucks. By the 25th and 26th of July all the rotor blades will
have arrived for transportation by helicopter to the wind park site.
Erection of the towers will begin on 2 July 2002, starting with
wind turbine 7.
|