Data & Facts
People
Goals
Tasks
The WEB
Participation

Advantages
Environment
Technology
Economics
Politics and Laws
Austria

Webcam
News and Press
Power Production

Panoramas
Photo Galleries
Downloads

Preview
Architecture

Site
Technology
Construction
Operation
Finances
Environment

First Steps
Altener
Measurements
5th FWP EU
Reports
Project Partners

Contact - Sitemap
Tauernwind Tauernwind Windpark Tauernwind Windpark
TauernwindWindparkTourismusTauernwindTauernwindWindenergieTauernwind

Site

Technology

Construction

Time Schedule
Access Road
Foundations
Transport
Wind Turbines
Power Cables
Companies


Operation

Finances

Environment

Wind Turbines

 

Data + Building Progress

Total number: 11

Building
Progress

Factory production
First sections of towers erected

100 %
100 %

15 Dec. 2002

Erection completed

11 WT's

Electrical installation

11 WT's

In operation

11 WT's

First phase of tower erection: 2-3 tower sections are installed. The remaining tower sections will be erected along with the machine house and rotor blades by means of a much larger crane.

The wind turbine manufacturer Vestas has been chosen to deliver the turbines.

   

 
 

6 December 2002
31 October 2002
8 October 2002
3 October 2002
30 August 2002
5 July 2002
21 June 2002
Data + Building Progress