Total cost of the Altener project amounted to: EUR 191,991.
ALTENER supported the project with EUR 70,000. Included in this
support was the 10 m and 49 m measurement campaigns, planning steps
from the Energiewerkstatt GmbH, the SODAR measurements and the model
calculations carried out by the German Wind Energy Institute (DEWI).The
proposal for the ALTENER funds was made in the autumn of 1998. A
positive answer was received in February 1999. The project began
officially in June 1999.
Remaining costs of the project were covered
by:
 |
|
|
Landesenergieverein Steiermark
Research Department of the Land Steiermark
Ministry of Economic Affairs
Over 50% from Tauernwind GmbH
|
18,131 EUR
21,802 EUR
7,267 EUR
74,791 EUR
|
|
 |
|
|
|